2015 Construction Schedule

Construction of the M-1 RAIL Streetcar line began in July 2014 and is anticipated to be complete in late 2016. During construction, our goal is to make sure that work is completed safely and quickly with as little disruption as possible to businesses, residents and visitors.

M-1 RAIL has created Construction Work Zones to better communicate about construction activities taking place near you. Zones will be used as a part of ongoing outreach to pinpoint where construction activities will be taking place so businesses, residents, employees and visitors will better understand how construction may impact their daily activities.

KEY:
MDOT
= MDOT Work (I94 & I75 bridge work)
DWSD = Detroit Water and Sewerage Department Work (Water main work, manhole modifications and storm sewer drain installation)
DTE = DTE Energy Work (Duct bank installation)
M-1 RAIL = M-1 RAIL Work (Track installation, roadwork and overhead cantenary system foundation)

2015 NORTH END/NEW CENTER DISTRICT

CURRENT CLOSURES – AT WOODWARD AVE.

  • W. Baltimore St.: 10/6/15 – (estimated 2 weeks)

UPCOMING CLOSURES – AT WOODWARD AVE. 

  • E. Baltimore St.: 10/19/15 – (estimated 2 weeks)
  • Amsterdam St.: 11/1/15 – (estimated 2 weeks)
  • Burroughs St.: 10/19/15 – (estimated 6 weeks)

 2015 MIDTOWN DISTRICT

CURRENT CLOSURES – AT WOODWARD AVE.

  • Garfield St.: 8/10/15 – (estimated 10 weeks)
  • Farnsworth St.: 10/9/15 – (estimated 3 weeks)
  • E. Hendrie St.: 6/5/15 – (estimated 24 weeks)
  • EB Warren Ave.: 10/9/15 – (estimated 6 weeks)

UPCOMING CLOSURES – AT WOODWARD AVE.

  • E. Forest Ave.: 11/9/15 – (estimated 3 weeks)

 2015 DOWNTOWN DISTRICT

CURRENT CLOSURES – AT WOODWARD AVE. 

  • E. Montcalm St.:  9/29/15 – (estimated 3 weeks)
  • Between Larned St. and Southern Terminus of Campus Martius (partial closures and lane impacts): 9/10/15 –  (estimated 9 weeks)

UPCOMING CLOSURES – AT WOODWARD AVE. 

  • Adams Ave.: 10/23/15 – (estimated 7 days)

*Construction schedule is subject to change.