FIRST QLINE STREETCAR TO ARRIVE THIS WEEK

Posted: 09/12/16

Delivery of First QLINE Vehicle Expected Wednesday

DETROIT – Detroit’s first QLINE streetcar will be delivered this week, M-1 RAIL announced today.

“Delivery of the first QLNE streetcar is an important milestone for this project,” said M-1 RAIL CEO Matt Cullen. “We’re bringing a sleek, modern vehicle of exceptional quality to Detroit. This project is one of the most innovative public transportation projects in the world today, from our landmark private-public partnership to the innovative off-wire battery technology that will power the QLINE, we couldn’t be more pleased to welcome the first QLINE vehicle.”

The first QLINE streetcar will arrive in Detroit Wednesday, nearly two months ahead of initial projections, keeping the QLINE on schedule for passenger operations to begin in Spring 2017.

“Receiving the first QLINE streetcar at this time will provide M-1 RAIL a greater opportunity to help Detroiters acclimate to the idea of sharing the road with a streetcar, and give us additional time for driver training,” said M-1 RAIL Chief of Operations, Paul Childs. “Over the next few weeks, we’ll complete the final assembly and mechanical checks needed before the streetcar makes its first appearance on Woodward Ave.”

The vehicle will depart today from Brookville Equipment Corporation, the only maker of streetcars to design and manufacture exclusively in the United States.

“The early delivery of this QLINE streetcar vehicle is a product of the outstanding working relationship we have experienced in our partnership with M-1 RAIL,” said Marion Van Fosson, President of Brookville Equipment Corporation. We look forward to delivering the next five vehicles and celebrating the QLINE opening with M-1 RAIL and the people of Detroit very soon.”

M-1 RAIL recently began the first of nearly 1,000 tests to be conducted before the start of passenger operations in 2017, operating a small motorized inspection car called a “speeder” to ensure the track is free of obstructions in advance of the first QLINE vehicle delivery.

The three-piece QLINE streetcars are each 66 feet long and will carry an average of 125 passengers per car. The QLINE will share the road, traveling with traffic on Woodward Ave. at speeds up to 35 mph. The QLINE streetcars will feature wi-fi access for passengers, vertical bicycle racks and and HVAC unit to keep passengers comfortable during all weather seasons. The QLINE will allow for station-level access for pedestrians as well as persons who use mobility assistance devices such as wheelchairs.

Construction Map

Weekly Email Updates

M-1 NEWS

QLINE start date announcement a few weeks away

Domeda Duncan , March 06, 2017

M-1 RAIL’s 2017 Community Update Meetings

Domeda Duncan , March 06, 2017

QLINE Testing Spread the Word

Domeda Duncan , February 24, 2017

TWEETS

Facebook Updates

Be engaged and get informed! Join M-1 RAIL as we host the March Community Advisory Council Meeting Thursday, March 9, 2017, at Triumph Church’s East Campus. The countdown to M-1 RAIL passenger ridership is on and there will be some adjustments to how you navigate the corridor. Please join M-1 RAIL for an important community conversation to learn about QLINE operations, testing schedule and the launch of our public safety education campaign.

This special CAC meetings will cover driving, cycling and walking along the Woodward Corridor, as we all now share the road. There will be a light dinner served and children’s activities will be available. There will also be sign language interpretation services available for community members who are deaf or hard of hearing. This meeting is open to ALL.

For more information and to RSVP please contact the M-1 RAIL Community Relations department at 313-483-8077 or via email at info@m1rail.org.
... See MoreSee Less

M-1 RAIL Community Advisory Council Meeting

March 9, 2017, 5:30pm - March 9, 2017, 6:39pm

Be engaged and get informed! Join M-1 RAIL as we host the March Community Advisory Council Meeting Thursday, March 9, 2017, at Triumph Church’s East Campus. The countdown to M-1 RAIL passenger ride...

View on Facebook