Most M-1 RAIL work to end for season by Thanksgiving

Posted: 09/02/16

*CORRECTION: Detroit Free Press Article

Author: Candice Williams
Article Originally posted on: Detroit Free Press

Orange barrels and barricades snarling traffic on Woodward for M-1 Rail project construction should be gone by Thanksgiving, officials said Thursday.

“The goal is to have it open to traffic,” said Paul Childs, COO of the M-1 Rail, which operates the QLine. “It doesn’t mean that it won’t have momentary lane drops. … New lights, new crosswalks, mid-block crossings will be in. All those kinds of things will be there.”

The news of when motorists should expect smoother travel along Woodward was among several updates Childs provided Thursday with Matt Cullen, M-1 Rail CEO. They spoke with media at the recently opened Penske Tech Center in the New Center area.

The M-1 Rail project has $187.3 million in committed funding, which will cover $142 million in capital costs, $23.9 million in preconstruction and administrative costs, and $21.4 million for streetcar operations, Cullen said.

The $142 million for capital costs is up 4 percent partly due to switching to Pennsylvania-based Brookville Equipment Corp., which officials said is the “leading provider of off-wire streetcar technology.” About 60 percent of the streetcar system will be off wire.

The first streetcar is expected to arrive this fall and all six by the end of the year, officials said.

Track installation is 83 percent complete, officials said.

The QLine is expected to start operations in early 2017. It will travel 3.3 miles downtown on Woodward to the New Center area.

Construction Map

Weekly Email Updates

M-1 NEWS

QLINE start date announcement a few weeks away

Domeda Duncan , March 06, 2017

M-1 RAIL’s 2017 Community Update Meetings

Domeda Duncan , March 06, 2017

QLINE Testing Spread the Word

Domeda Duncan , February 24, 2017

TWEETS

Facebook Updates

Be engaged and get informed! Join M-1 RAIL as we host the March Community Advisory Council Meeting Thursday, March 9, 2017, at Triumph Church’s East Campus. The countdown to M-1 RAIL passenger ridership is on and there will be some adjustments to how you navigate the corridor. Please join M-1 RAIL for an important community conversation to learn about QLINE operations, testing schedule and the launch of our public safety education campaign.

This special CAC meetings will cover driving, cycling and walking along the Woodward Corridor, as we all now share the road. There will be a light dinner served and children’s activities will be available. There will also be sign language interpretation services available for community members who are deaf or hard of hearing. This meeting is open to ALL.

For more information and to RSVP please contact the M-1 RAIL Community Relations department at 313-483-8077 or via email at info@m1rail.org.
... See MoreSee Less

M-1 RAIL Community Advisory Council Meeting

March 9, 2017, 5:30pm - March 9, 2017, 6:39pm

Be engaged and get informed! Join M-1 RAIL as we host the March Community Advisory Council Meeting Thursday, March 9, 2017, at Triumph Church’s East Campus. The countdown to M-1 RAIL passenger ride...

View on Facebook